# Long-lead electrical gear: planning around 2026 switchgear and transformer waits

Johquin Yanez · Project Manager · November 13, 2026

> In 2026 the transformer, not the concrete, sets your schedule. Here is how commercial owners and developers in El Paso and Las Cruces plan procurement, temporary power, and design so long-lead electrical gear does not blow up the job.

A developer walked us through a retail-and-office shell last year that had everything ready. The pad was graded, the caliche was handled, the structural steel had a delivery date, and the crews were lined up. The one thing that was not ready was a piece of equipment the size of a refrigerator sitting in a factory queue two years deep. The transformer had not been ordered. Every other number in the schedule was now fiction.

For most of the last two decades, electrical gear was something you specified during design and bought during construction. That order is dead. In 2026, on a commercial job of any real size, the transformer is usually the first thing you buy and the last thing that arrives. If you plan the building the old way, the equipment sets your schedule and you find out too late.

## The lead times, plainly

Here is where the numbers stood going into 2026. Use them to gut-check any vendor quote.

- **Large medium-voltage power transformers:** about 128 weeks, roughly two and a half years, from primary US manufacturers in early 2026. In constrained parts of the market, quotes stretched to four years.
- **Switchgear:** commonly 90-plus weeks at some manufacturers, with delivery quotes running 52 to 78 weeks depending on the vendor.
- **Circuit breakers and distribution panels:** frequently 40 to 60 weeks.
- **New distribution transformers:** roughly 50 weeks, driven partly by utilities that once ordered 2,000 units a year now ordering 4,000 to 5,000.

None of these are promises. They are quotes that move as factory slots fill. The honest way to read them is as a floor, not a ceiling.

## Why the wait is not going away

This is not a backlog that clears in a quarter. It is structural. The data center and artificial intelligence construction boom is eating the majority of major manufacturer capacity, and it is not the only buyer at the counter. Grid upgrades, renewable interconnection, industrial electrification, and normal utility replacement cycles are all reaching for the same transformers, switchgear, and breakers at the same time.

Underneath all of it is a materials problem. Transformer cores need grain-oriented electrical steel, a silicon-iron alloy made by only a handful of mills on the planet, and copper for the windings is tight too. You cannot re-tool a steel mill to make that alloy in a season. It takes years. Nearly 1.8 billion dollars of new North American transformer manufacturing investment is underway, which is real, but that capacity does not show up in meaningful volume until roughly 2027 to 2028. For a job breaking ground in 2026, that relief is not on your timeline.

## How this blows up a commercial schedule

The failure looks the same almost every time. Design finishes, the team moves to buy equipment, and only then discovers the transformer is 100-plus weeks out. Now the whole job waits on one item, no matter how ready the civil work, the generators, the switchgear, or the installation crews are.

There is a money version of this too, and it is worse. Most construction lenders require committed equipment procurement before they release construction draws. A transformer with a confirmed manufacturer delivery date functions as underwriting collateral. Without that confirmation, teams often cannot access the capital to start civil work at all. So the missing order does not just delay power. It can freeze the money that pays for the dirt.

## Order early, and design so you can

The fix is not complicated, but it changes the order of operations. Procurement strategy becomes a critical-path item you decide up front, not a package you open after design development.

That means locking the transformer specification during early engineering, not late. The parameters that let a factory build your unit are the voltage, the power rating, the impedance, the cooling method, the applicable standards, and the accessories and testing requirements. When those get finalized late, the entire project waits even though everything else is ready. Nail them down early and the long-lead order can go out while the rest of the design is still in motion.

A few moves that protect the schedule:

- **Buy the long-lead items first.** On many jobs the transformer order precedes the slab. Treat it as the anchor date the rest of the schedule hangs on.
- **Lock the electrical basis of design early.** Voltage, rating, impedance, cooling, and standards should be settled before the drawings are fully done, so the order is not held hostage to a late decision.
- **Get the utility in the room early.** El Paso Electric on the Texas side, or your Las Cruces utility on the New Mexico side, has its own equipment and interconnection queue. That queue can sit on your critical path, and it is not something you can expedite with a purchase order.
- **Design around what you can actually get.** If a particular voltage class or switchgear configuration carries a punishing lead time, an equivalent design that uses in-stock or shorter-lead gear can save months. That tradeoff belongs in preconstruction, not in a change order later.

## Where temporary power fits

Temporary power buys weeks. It does not buy years. Temporary generators or a utility temporary service can run construction, commissioning, and testing, and in some cases carry a partial early opening while permanent gear is still in transit. What it usually cannot do is stand in for permanent switchgear and transformers at full occupancy.

The place teams get burned is treating temporary power as a plan instead of a bridge. It is genuinely useful for keeping crews productive and hitting an interim milestone. It is not a reason to delay ordering the permanent equipment, because the permanent gear is exactly the thing you cannot conjure on short notice.

## The short version

If you are planning a commercial project in the Borderplex in 2026, put the electrical equipment at the front of your thinking, not the back. Confirm lead times in writing. Lock the transformer specification during early engineering. Place the long-lead order before you pour. Loop the utility in early, because their queue matters as much as the factory's. And use temporary power as a bridge, never as the plan.

If you have a project on the board and you are not sure whether your electrical procurement is on the right timeline, send your plans or your bid set to our estimating team for an honest read. We will tell you where the long-lead items sit against your schedule, whether we end up doing the work or not.

## FAQ

### What are transformer and switchgear lead times in 2026?

In early 2026, large medium-voltage power transformers from primary US manufacturers reached about 128 weeks, roughly two and a half years, and constrained parts of the market ran as long as four years. Switchgear was quoted at 52 to 78 weeks depending on vendor, and distribution panels and breakers commonly ran 40 to 60 weeks. New distribution transformers hit roughly 50 weeks. Treat any number a vendor gives you as a quote to confirm in writing, not a promise, because slots move.

### Why are electrical equipment lead times still so long in 2026?

The shortage is structural, not a temporary backlog. Data center and AI facility construction is consuming most major manufacturer capacity, while grid upgrades, renewable interconnection, and industrial electrification all compete for the same transformers, switchgear, and breakers. A core bottleneck is grain-oriented electrical steel, the silicon-iron alloy used in transformer cores, which only a handful of mills worldwide produce, and re-tooling a mill takes years. New North American manufacturing investment will not add meaningful capacity until roughly 2027 to 2028.

### When should I order the transformer for a commercial project in El Paso?

Order it before you finish design, not after. In 2026, electrical equipment is a front-end feasibility input, not a procurement package you open during construction. Lock the key transformer parameters, voltage, power rating, impedance, cooling method, and applicable standards, during early engineering so the order can be placed. A facility that needed main power by late 2026 would have had to order back in late 2023, so the practical rule is simple: the transformer is usually the first thing you buy, well ahead of the slab.

### Can temporary power keep a project moving while gear is on order?

Sometimes, for parts of the work. Temporary generators or a utility temporary service can power construction, testing, and even a partial early opening, but they rarely replace permanent switchgear and transformers for full occupancy. Temporary power is a bridge that buys weeks, not a substitute that buys years. Coordinate early with El Paso Electric or your Las Cruces utility, because their own equipment and interconnection queue may sit on the critical path too.

Source: https://expertconstruction.group/blog/long-lead-electrical-switchgear-2026
